Hr 90% done
need to finalize fishing rod attachment and brackets
then use quad draw to make leather wrapping and a sweep mesh for the rope
Schedule
Week 1
- Proxy Pass (done)
- Research (done)
Week 2
- HR (ready to Sculpt)
Week 3
- Sculpt of wood and weld parts
- final pass GR/Retop (for sculpted parts if needed)
- final bake
- First pass textures
Week 4
- Final Textures
- final in engine